ERCOT will not issue a new voluntary medium-load RFI after Monday.
Market Notice M-B091426-02, sent September 24, 2026, sets Monday, October 5, 2026 as the last day ERCOT will issue a new voluntary Medium Load RFI.
INSIGHTS / POWER & ENERGIZATION
The useful power date is the date a defined tenant load can operate under accepted service conditions. Compare permanent supply, a smaller opening phase and a bridge route against that same endpoint before releasing long-lead equipment.
A study position, a utility construction milestone and permission to load a building describe different outcomes. A campus can have progress on all three and still lack a supported opening date. The unresolved condition may be an upstream work, a payment, a protection requirement or an incomplete campus connection.
Bridge generation can move the constraint rather than remove it. Fuel, air authorization, noise, operating duty and transition to permanent service must fit the same tenant requirement. Installed generating capacity alone does not establish a usable alternative.
Power discussions often compress a conditional sequence into one date. Provider works and campus works then advance on different assumptions about readiness, load acceptance and who bears delay. Equipment orders harden those assumptions before the service boundary has been settled.
A bridge proposal may be compared with grid energy cost while its full operating obligations remain outside the calculation. The permanent route can also be underestimated if security, network works, testing and a slower tenant ramp are omitted.
Define the opening load at the point of service, its ramp, power quality and operating limits. Work backward through load acceptance, energization, testing, campus electrical completion and provider prerequisites. Mark which dates are supported by counterparties and which remain planning assumptions.
For each route, identify the last responsible release date for land, equipment and fuel or service commitments. Test a delayed permanent connection and an unavailable bridge asset. A route is viable only if its residual service and cost exposure remain acceptable under those conditions.
Waiting for permanent service can avoid a temporary operating system, but may require a revised tenant date. Opening with a smaller supported load can retain some occupancy while limiting the ramp. Bridge generation can be considered where its technical, service and authorization basis is demonstrated, with a defined duration and exit.
Price the whole service period through transition. Include temporary assets, fuel arrangements, retained grid obligations, testing and removal or conversion. Do not credit a bridge with unlimited extension or assume its land remains available for permanent infrastructure.
Swipe or scroll to compare all columns.
| Route | When it fits | Tradeoff | Evidence before commitment |
|---|---|---|---|
| Permanent service at the full phase load | The tenant date can follow a supported permanent-service sequence. | Concentrates dependence on provider and campus completion. | Documented prerequisites, funded works and load-acceptance criteria. |
| Smaller initial load with a staged ramp | A limited service position and tenant operating basis can agree. | Earlier partial use may be possible; later capacity stays conditional. | Written load limits and a tenant ramp tied to future acceptance. |
| Time-limited bridge supply | The proposed operating duty, fuel and service arrangement are supportable. | Additional capital and operating exposure, plus a transition obligation. | Technical validation, applicable authorizations and a funded exit route. |
Sitebraid would reconcile the provider record, campus electrical basis and tenant ramp into a sequence ending at accepted load. Each unresolved condition is tied to the specific release it prevents.
We would assemble the permanent, staged and bridge cases with the electrical, fuel and permitting specialists. Each case includes residual grid payments, operating limits, land use and the consequences of a later connection.
We would define which procurement can proceed against the documented position and which release requires further provider or technical evidence. The chosen route includes a transition test and a decision date for changing the promised ramp.
Distinguish preliminary correspondence, completed studies and contractual commitments. Retain the conditions attached to each. Verify the applicable provider process for the actual site before treating another campus schedule as evidence.
Protect required reserve and the permanent electrical corridor. Put a limit on bridge duration and expenditure, with a trigger to resize or defer load if permanent service moves beyond that limit. Technical acceptance and authorized operating procedures remain with the responsible specialists.
Require a supported route from the present service position to accepted tenant load, including conditional works, funding, operating limits and transition obligations. The result should make clear what can be ordered now and what evidence must arrive before the next irreversible expenditure.
Before the next electrical equipment release, request the current provider conditions and place them beside the tenant ramp and campus testing sequence. Choose full permanent service, a smaller initial load or a validated bridge, and record the condition that would force that choice to change.
Illustrative assignments that connect a potential owner problem to evidence, alternatives and acceptance criteria. They are not claimed client results. Dated public context and sources appear in each article.
Market Notice M-B091426-02, sent September 24, 2026, sets Monday, October 5, 2026 as the last day ERCOT will issue a new voluntary Medium Load RFI.
Separate security drawdowns, CIAC and advance procurement before the same phase creates two liquidity demands ahead of tenant revenue.
On-site generation can support a campus strategy. It also creates a fuel, permitting and delivery scope that must stand up on its own.
Texas campus owners should fund a deliverable first phase, not mistake a conditional grid classification for a power commitment.